1141. Pick up the excavation where measurements are made in square metres for payment.
Ordinary cuttings up to 1 m
Surface dressing up to 15 cm depths
Surface excavation up to 30 cm depths
Both (b) and (c)
1142. Pick up the correct statement from the following:
If the bed level is above N.S.L. the canal is called fully in baking and the berms are designed as 3 d where d is full supply depth of water (F.S.D.)
Area of canal in cutting BD + Sd 2 where B-bed width, d depth of cutting and S is the side slope
If F.S.L. is above N.S.L the canal is called partly in cutting and partly in filling and berms are designed as 2d where d is full supply depth
All the above
1144. Pick up the correct statement from the following:
Pointing is measured in sq.m
Plastering is measured in sq.m
Glazing is measured in sq.m
All the above
1146. For the construction of buildings, the subheads of the estimate are
Earthwork, Concrete work, Brick work
Brickwork, Stone work, Roofing
Brickwork Flooring, Wood work, Steel work
All the above
1149. The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is
b-rd) 2/(r-s)
b-rd) 2/(r+s)
1/2(b+rd) 2/(r-s)
b-rd) 2/(s-r)
1151. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken
1.80 litres for 5 to 10 users
1.20 litres for 15 users
1.35 for 20 users
All the above
1153. সিমেন্টের গুণাগুণ নির্ণয়ের জন্য কয়টি করীক্ষা করা হয়?
5
7
6
8
1154. নিচের কোন উপাদানটি কাচের স্বচ্ছতা বৃদ্ধি করে?
সোডিয়াম
ম্যাগনেসিয়াম
সিলিকা
অ্যালুমিনা
1155. In the mid-section formula
The mean depth is the average of depths of two consecutive sections
The area of mid-sections is calculated by using mean depth
The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
All of the above
1156. Pick up the incorrect statement from the following:
No deduction is made for the volume occupied by reinforcement
No deduction is made for the openings upto 0.1 sq.m
No deduction is made for volumes occupied by pipes, not exceeding 100 sq.cm in crosssection
None of these
1158. পোর্টল্যান্ড সিমেন্ট তৈরি করার সময় জিপসাম দেওয়া হয় কেন?
সিমেন্ট জমাট বাঁধার সময় কমানোর জন্য
সিমেন্ট জমাট বাঁধার সময় বাড়ানোর জন্য
পোড়ানোর তাপমাত্রা কমানোর জন্য
ক্ষারতা কমানোর জন্য
1159. সর্বনিম্ন কত মিমি চালুনি দিয়ে অতিক্রম না করলে নমুনাকে কোর্স এলিগেট হিসেবে ধরা হয়?
4.75 mm
2.36 mm
5 mm
2.45 mm
1160. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm. is termed as
Excavation
Surface dressing
Cutting
Surface excavation