MCQ
601. কোন বিষয়টি নির্ধারণের জন্য কনক্রিটের প্ল্যাম্প টেস্ট করা হয়?
strength
Durability
water cement ratio
workability
602. If ID is the depth of scour below original bed, then the width of launching apron is generally taken as
1.2 D
1.5 D
2.0 D
2.5 D
603. Workability of concrete is measured by (.. যারা কংক্রিটের কার্যক্ষমতা পরিমাণ করা হয়।)
cylinder
cube test
Slump test
setting time test
604. Efflorescence in cement plaster is due to excess of. (কিসের আধিক্যের কারণে সিমেন্ট প্লাস্টারে Efflorescence হয়?)
Alumine
Silica
Lime
Alkali
605. কোনটি Retaining structure?
buttress wall
bridge abutment
box culvert
mohr
606. অনিরাপদ কাঠামোকে temporary support প্রদানের ব্যবস্থাকে কি বলে?
underpinning
scaffolding
shoring
jacking
607. The net head under which the turbine reaches its peak efficiency at synchronous speed is called
Design head
Rated head
Gross head
Operating head
608. কোন materials টি membrane curing এ ব্যবহার করা হয় না?
Bituminous emulsion
Lime emulsion
Wax emulsion
Plastic emulsion
609. নিচের কোনটি Bituminous materials properties -
Consistency
Durability or resistance of weathering
Rate of curing
Resistance to water action
610. Tiles এ glazing কেন করা হয়?
To increase hardness
To increase imperviousness
To increase porousness
কোনটিই নয়
611. A first class brick when immersed in cold water 24 hours should not absorb water more than (প্রথমে শ্রেণির ইট ২৪ ঘণ্টা পানিতে ভেজানোর পর..... এর অধিক পানি শোষন করিবে না)
10%
20%
15%
25%
612. An ideal rise in a stair is (একটি সিঁড়িতে আদর্শ রংব হল-)
100 mm
125 mm
150 mm
250 mm
613. Pick up the correct statement from the following:
The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like duration
To obtain the ordinates of storm hydrograph, the ordinates of unit hydrograph are multiplied by the multiplying factor
The multiplying factor for storm hydrograph may be obtained by dividing the run off in mm by 25 mm
All the above
614. For increasing setting time of concreate, what type of admixture is used?
accelerator
retarder
water reducing
air entraining
615. A unit hydro graph has one unit of
Rainfall duration
Rainfall excess
Time base of direct runoff
Discharge
616. Initial setting time (minimum) of ordinary Portland cement is- (সিমেন্টের প্রাথমিক জমাটবদ্ধতার ন্যূনতম সময় কত-)
60 minutes
45 minutes
30 minutes
20 minutes
617. For efficient working of a control meter, its throat length is approximately kept
Equal to the critical depth
Twice the critical depth
Three times the critical depth
Four times the critical depth
618. When a constant discharge 2.91 litres/sec. was obtained in a pumping test, the draw downs in the test wells at 3 m and 6.184 m were 2.6 m and 0.3 m respectively. If over-all depth of the pumping well was 16 m, the permeability of the soil, is
0.0005 cm/sec
0.001 cm/sec
0.002 cm/sec
0.01 cm/sec
619. ভরাট মাটির ধ্বংস প্রতিরোধে নিচের কোন স্ট্রাকচার ব্যবহৃত হয়?
Retaining wall
Boundary wall
shear wall
Vertical wall
620. Slack Time refers to অথবা Slack time কী ?
An activity
An event
Both event and activity
None of the above