41. In a pre-stressed member, it is advisable to use:
Low strength concrete only.
High strength concrete only.
Low strength concrete but high tensile steel.
High strength concrete and high tensile steel.
42. The moment at a hinge will be:
Infinity
Zero
Depends upon acting force
None of these
43. The type of bond in a brick masonry containing altenate courses of stretcher and headres is called:
Flemish bond
English bond
Stretcher bond
Header bond
44. The ratio of specific weight of a liquid to the specific weight of pure water at a standard temperature is called-
Density of liquid
Specific gravity of liquid
Compressibility of liquid
Surface tension of liquid
45. Machine foundation is subjected to:
Static loads
Wind loads
Dynamic loads
Static and dynamic loads
46. The bending moment of cantilever beam shown below figure at 'A' is:
Zero
8 T-m
16 T-m
14 T-m
47. Disinfection of water results in-
Removal of turbidity
Removal of hardness
Killing of disease bacteria
Removal of taste
48. Loss Angeles testing machine is used to conduct:
Abrasion test
Attrition test
Crushing strength test
Impact test
49. Which types of forces are generated during earthquake?
Vertical Shear
Horizontal Shear
Combination of both horizontal & vertical shear
Bending moment
50. The roof type suitable in plains where rainfall is meagre and temperature is high is:
Pitched and sloping roof
Flat roof
Shell roof
None of these
51. The proportion of lime and sand in the mortar normally used in brick constructions are:
1:2
1:6
1:4
1:8
52. Plane and geodetic surveying are classification of surveying based on:
Methodology
Earth's curvature
Ojbect of survey
Instrument
53. When a cohesionless soil attains quick condition, it looses:
Shear strength
Bearing capacity
Both (ক) and (খ)
Neither (ক) and (খ)
54. The maximum permissible limit for iron in drinking water is:
0.1 mg/L
0.3-1 mg/L
2-2.5 mg/l.
5 mg/L
55. The entrained air in concrete-
increase workability
decrease workability
decrease resistance to weathering
increase strength
56. The transverse reinforcements provided at right angles to the main reinforcements in a slab--
Distributed load
Resist the temperature stress
Resist the shrinkage stress
All of the above
57. A soil consolidated under the existing over- burden pressure, is called:
Pre-consolidated
Normally consolidated
Over-consolidated
None of these
58. After pre-stressing process is completed, loss of stress occurs due to-
Shrinkage of concrete
Creep of concrete
Elastic shortening of concrete
All of the above
59. Standard BOD is measured at:
20°C-1 day
25°C-3 day
20°C-5 day
30°C-5 day
60. Uniformity coefficieny of a soil is:
equal to or greater than 1
equal to 1
equal to or less than 1
none of these