MCQ
1021. Size, capacity and materials need be specified for
Bib-cocks
Stop-cocks
Ball valves
All the above
1022. Berms are provided in canals if these are
Fully in excavation
Partly in excavation and partly in embankment
Fully in embankment
All the above
1023. For 100 sq. m cement concrete (1: 2: 4) 4 cm thick floor, the quantity of cement required, is
0.90 m3
0.94 m3
0.98 m3
1.00 m3
1024. If tensile stress of a steel rod of diameter is 1400 kg/cm2 and bond stress is 6 kg/cm2, the required bond length of the rod is
30 D
39 D
50 D
59 D
1025. In case of laying gullies, siphons, intercepting traps, the cost includes
Setting and laying
Bed concreting
Connection to drains
All of these
1026. Pick up the incorrect statement from the following:
Dimensions are measured to the nearest 0.01 m
Areas are measured to the nearest 0.01 sq.m Book
Cubic contents are measured to the nearest 0.1 cum
Weights are measured to the nearest 0.001 tonnes
1027. Pick up the incorrect statement from the following:
The built up covered area at the floor level of any storey of a building is called plinth area
The usable covered area of the rooms of any storey of a building is called carpet area
The carpet area of a building along with area of its kitchen, pantry, store, lavatory, bath room and glazed veranda, is called floor area
None of these
1028. For 12 mm thick cement plastering 1: 6 on 100 sq.m new brick work, the quantity of cement required, is
0.200 m3
0.247 m3
0.274 m3
0.295 m3
1029. The correct Prismoidal formula for volume is
D [first area + last area + Even area + 2 odd areas)
D/3 [first area + last area + 4 Even area + 2 odd areas]
D/3 [first area last area + 2 Even area + 4 odd areas]
D/6 [first area + odd areas]
1030. The inspection pit or chamber is a manhole provided in a base drainage system
At every change of direction
At every change of gradient
At every 30 m intervals
All the above
1031. The expected out turn of half brick partition wall per mason per day is
1.5 m3
2.0 m3
4.0 m2
5.0 m2
1032. The height of the sink of wash basin above floor level is kept
60 cm
70 cm
75 cm to 80 cm
80 cm
1033. The damp proof course (D.P.C.) is measured in
Cub. m
Sq. m
Metres
None of these
1034. The volume is measured correct to the nearest
0.01 cum
0.02 cum
0.03 cum
0.04 cum
1035. The slope of the outlet of 'P trap' below the horizontal is kept
8°
10°
12°
14°
1036. The item of steel work which is measured in sq.m, is
Collapsible gates
Rolling shutters
Ventilators and glazing
All the above
1037. The floor area includes the area of the balcony up to
100%
75%
50%
25%
1038. The cross-sectional area of the embankment of a canal fully in embankment in the given figure is
½ (+) h
(+) h+sb²
(+)+2sh
2 [(+) (b+sh²)]
1039. The 'centre line method' is specially adopted for estimating
Circular buildings
Hexagonal buildings
Octagonal buildings
All the above
1040. The weight of an item is measured correct to nearest
0.25 kg
0.50 kg
0.75 kg
1.00 kg