MCQ
21161. The reception signal is- [MES-16]
outer signal
home signal
both a & b
none of these
21162. A water-bound macadam road is an example of- [BGFCL-17]
rigid pavement
semi-rigid pavement
flexible pavement
none
ব্যাখ্যা: A pavement which consists of a mixture of a asphalticor bituminous matedrial and aggregate placed on a good quality and compacted granular material is termed as flexible pavement. Example- Water bound macadam road.
21163. Asphalt cement usually used in Bangladesh has the penetration range of- [MES-16]
AC 40-50
AC 85-100
AC 60-70
AC 120-150
21164. A road connecting two towns is called
country road
urban road
highway
none of these
21165. The roads connecting capital cities of states are called-
national highway
state highway
express way
capital highway
21166. প্রি-কাস্ট পাইলের দৈঘর্্য
3-15m
15-440m
4.5-30m
2-40m
ব্যাখ্যা: যেখানে অতিরিক্ত ভারবহন করার প্রয়োজন হয় সেখানে প্রি-কাস্ট পাইল ব্যবহার করা হয়। এ পাইলের ব্যাস ৩৫-৬৫সেমি
21167. Carriage-way is protected by --- wide shoulders.
0.5 to 1.25
1.25 to 2
2 to 4
4 to 6
21168. নিচের কোন ক্ষেত্রে নিট সিমেন্ট ফিনিশিং করা হয় না?
মেঝে
স্কাটিং
ড্রেন
টয়লেট
ব্যাখ্যা:
সিমেন্ট ফিনিশিং হচ্ছে স্বল্প ব্যয়ের একপ্রকার ফ্লোর ফিনিশিং। এজন্য মেঝের ক্ষেত্রে নিট সিমিন্ট ফিনিশিং করা হয় না। কারণ মেঝেতে নিট সিমেন্ট ফিনিশিং করলে ভালো মসৃণ হয় না
21169. The term used for major important roads of a country is-
country road
urban road
highway
none of these
21170. How many parts of a pavement? [BREB-17]
3
5
4
6
ব্যাখ্যা: There are 4 part of a pavement such as subgrade, sub-
base. Base course and surface course or wearing course,
21171. The asphalt naturally available is
Surface asphalt
Lake asphalt
Rock asphalt
All of above
21172. For the water-bound macadam road, the recommended camber is-
1 in 24 to 1 in 30
1 in 30 to 1 in 48
1 in 48 to 1 in 80
1 in 80 to 1 in 120
21173. What is the weight for 1 cft RCC slab of thickness 0"-4"? [MES-16]
150 lb
100 lb
50 lb
60 lb
ব্যাখ্যা: ব্যাখ্যা
4''*150/12=50 lb
21174. The road surfacing should be-
impervious
stable
durable
all of these
21175. The slope of the line joining the crown and edge of the road surface is known as-
cross-fall
camber
cross-slope
any one of these
21176. The thickness of base, is no case, should be more than-
0cm
20cm
15cm
30cm
21177. The superstructure of a road is called-
wearing layer
wearing course
road surface
any one of these
21178. The Central Road Organisation (CRO) was set up in-
1930
1948
1934
1956
21179. The camber recommended for water-bound macadam roads is-
1 in 24 to 1 in 30
1 in 30 to 1 in 48
1 in 48 to 1 in 60
1 in 60 to 1 in 80
21180. The foundation of a road is also called-
soling
base
either a or b
none of these